fbpx
Sunday, December 22, 2024
HomeNewsLegal NoticesSECTION 00 11 13 ADVERTISEMENT FORBIDS

SECTION 00 11 13 ADVERTISEMENT FORBIDS

TITLE: Lake Superior Schools Two Harbors and Silver Bay Bus Garage

LOCATION OF WORK:

Two Harbors Bus Garage
3rd and 6th Avenue
Two Harbors 55616
Silver Bay Bus Garage
Edison Blvd.
Silver Bay 55614

OWNER:

Independent School District #381 3 Lake Superior School District
1640 County Highway 2
Two Harbors, Minnesota 55616

CONSTRUCTION MANAGER:

ICS
1331 Tyler Street NE, Suite 101
Minneapolis, MN 55413
(763) 354-2670
Contact: Ekalath.sophaphanh@ics-builds.com

ARCHITECT:

Wold Architects and Engineers.

332 Minnesota Street, Suite W2000

St. Paul, Minnesota 55101

(651) 227-7773

sbagley@woldae.com

STRUCTURAL:

Northland Consulting Engineers

102 South 21st Avenue West, Suite 1

Duluth, Minnesota 55806

(218) 727-5995

mark@nce-duluth.com

MECHANICAL ENGINEER:

CMTA

525 S Lake Avenue, Suite 222

Duluth, Minnesota 55802

(218) 722-3060

ben.felland@cmta.com

ELECTRICAL ENGINEER:

CMTA

2201 12th Street N, Suite E

Fargo, North Dakota 58102

(701) 280-0500

andy.bartsch@cmta.com

CIVIL ENGINEER: CMTA

2201 12th Street N, Suite E

Fargo, North Dakota 58102

(701) 280-0500

steve.schilke@cmta.com

PROJECT DESCRIPTION:

The project consists of multiple work scopes for all of the work necessary for the renovations and additions of two bus garages .

BID DATE AND LOCATION:

Sealed Bids will be received at District Office 1640 County Highway 2,Two Harbors, Minnesota 55616 then publicly opened and read aloud. Bids will be re­ceived and stamped-in prior to 3:30 PM on November 7, 2023. Bids submitted after allotted time will be discarded, NO EXCEPTIONS.

EXAMINATION OF DOCUMENTS:

Bidders may view drawings and specifi­cations for the project at the office of the Construction Manager.

For Electronic access to the bidding doc­uments, please contact Angie Stahnke at (218) 336-5901 angie.stahnke@ics-builds. com. The Construction Manager can also provide locations of Builders Exchanges holding plans for contractors to access. Bidders are responsible for any and all costs associated with the production of plans and specifications for their use.

BIDDING REQUIREMENTS:

Each Bidder must comply with the follow­ing requirements to reassure acknowledg­ment and recognition of their Bids:

Bids must be accompanied by Bid security in the form of a certified check, cashier’s check, or Bid bond in the amount of 5% of the base Bid submitted, made payable to the owner, as guarantee that Bidder will, if awarded, enter into contract in accordance with contract documents and submitted Bid.

Submit Bid on the prescribed form, which is furnished with the specification, with full name and address of the Bidder.

Completely fill in all blank spaces on the Bid Form, in ink or typewriter, in both words and figures.

Sign in longhand, executed by a principal duly authorized to enter into an agreement. If a Bidder is a co-partnership, then signa­tures on the Bid shall be by an authorized member of the firm, with names and ad­dresses of each member of partnership.

Base Bid and all alternate Bids shall be stated both in writing and in figures. In all cases, written and numerical figures must agree; otherwise at Owner’s option, it shall be cause for rejection of Bid. Complete form without alterations.

Submit alternate prices (Bids) for either increasing or decreasing the costs, as called for on Bid form and Description of Alternates. Submit a Bid for all alternates.

Owner may make such investigations as they deem necessary to determine the ability, competency, and responsibility of the Bidder to perform the work. Any Bidder shall furnish to the Owner all such information and data for this purpose, as the Owner may request. Owner reserves the right to reject any Bid if the evidence submitted by, or investigation of, such Bidder fails to sat­isfy the Owner that such Bidder is properly qualified to carry out the obligations of the contract and to complete the Work con­templated therein. The competence and responsibility of Bidder will be considered in making an award, including, but not lim­ited to; (1) proof of financial responsibility, (2) quality of similar work, (3) amount of experience with similar projects, (4) facil­ities, personnel and equipment, (5) repu­tation for performance, and (6) the ability to complete the work within specified time. Owner reserves the right to reject any Bid where there is reasonable doubt as to the qualifications of the Bidder.

Owner reserves the right to: (1) accept Bidder’s Base Bid only, (2) accept any one or more of bidder’s Alternate Bids, in any order regardless of the order in which they were listed, (3) reject all Bids, (4) award contract based on their investiga­tion of Bidders, as well as acceptance of alternates, all of which the Owner deems to be in their best interest, (5) waive infor­malities or minor irregularities in Bids and waive minor irregularities or discrepancies in Bidding procedure.

Upon award of Contract, Contractor shall provide AIA A312 Performance and Pay­ment Bonds in the amount of 100% of Contract Sum in accordance with General Conditions and Amendments to General Conditions.

BIDDING DOCUMENTS & SITE REVIEW:

Each Bidder (including subcontract Bidder where appropriate) is advised to visit the site and to fully inform themself and record their own investigations as to the extent of the Work, the extent of the work performed by other contractors under other construc­tion packages, conditions under which the Work is to be performed, existing buildings and streets, conditions of the area, exist­ing utilities and other features, type of soil, available facilities and difficulties that may be encountered in connection therewith, and other relevant items which will affect their Bid or the Work.

Prior to submitting a Bid, each Bidder is required to examine all of the bidding requirements, all Contract Documents, all drawings, and specifications for the Project (including those primarily for other Subcontracts). Contractors shall become thoroughly familiar with the scope of the Project and all factors and items of work which will affect their Bid or the Work, whether shown or specified in documents primarily for Work of others or Work of this Contract.

No extras will be allowed to the Contractor as a result of misunderstanding the extent of scope of the Work as a result of their fail­ure to study and record their own findings. Submission of a Bid shall be proof that such examinations have been made and that Bidder has recorded their own investi­gation and has become thoroughly familiar with all contract documents (including all addenda). The failure or omissions of any Bidder to examine any form, instrument or document shall in no way relieve any Bidder from any obligation in respect to their Bid. Nor shall it be the responsibility of ICS or its counterparts to ensure you have read all documentation. This is the sole responsibility of the Bidder and its Sub-Contractor(s).

PRE-BID CONFERENCE:

A Pre-Bid conference will be held at 3:00 PM on October 24, 2023 at Silver Bay Bus Garage and 4:30 PM at Two Har­bors Bus Garage. No extras will be al­lowed because of the Bidder’s misinterpre­tation as to the amount of work involved, Bidder’s own error, negligence, or failure to examine the site.

START DATE:

Work will begin after receipt of the signed contract from the Owner. The anticipat­ed award date is December 20, 2023. Pre-construction and submittals work re­lated to the project is to commence imme­diately after receipt of the signed contract. The onsite work will begin on the premises no later than April 29, 2024.

SUBSTANTIAL AND COMPLETION DATE:

Owner requires all work to be substantially completed by August 23, 2024.

END OF SECTION 00 11 13

RELATED ARTICLES
- Advertisment -

Most Popular