CARRY OVER PROJECTS

City of Two Harbors 2024 & 2025 Street & Utility Improvements (SAP 038-636-001)

Location: City of Two Harbors

  • 5th Street (CSAH 36) – 4th Ave to 7th Ave
  • 6th Avenue (7th St to 4th St)
  • 5th Avenue (Waterfront Dr to 5th St)
  • 4th Avenue (Waterfront Dr to 3rd St)

Work Description: Street & Utility

Reconstruction (Water utility, sewers, curbs, side­walks, pavement).

  • Finish 5th Street and 4th Ave
  • Reconstruction.
  • Complete 6th Ave and 5th Ave
  • Reconstruction

Construction Timeframe: Mid-April thru October

Cost: $8 million

Traffc Impacts: Road Closures

  • 5th St, 5th Ave, 6th Ave.
  • Waterfront Dr, 7th St will be closed at 6th
  • Avenue (short duration)

NEW PROJECTS

2025 Seal Coat Project (SAP 038-626-008)

Location: City of Two Harbors, CSAH 26 and Various City Streets and Alleys
Work Description: Preventative maintenance in­cluding bituminous seal coat, fog seal and pavement marking.
Construction Timeframe: Between June & September
Cost: $270,000
Traffic Impacts: Temporary lane & road closures, traffic flagging.

Hawk Hill Road Bridge Replacement  (SAP 038-598-009 (CP 102-024-001))

Location: CR 102, Hawk Hill Road, Bridge over Knife River
Work Description: Remove and replace bridge over Knife River and reconstruct approaches.
Construction Timeframe: June thru October
Cost: $2.1 million
Traffic Impacts: Temporary one-lane bypass road and temporary bridge

CR 105 – 8th Street Resurfacing (CP 105-022-001)
Location: 8th Street from Hwy 61 (7th Street) to 16th Avenue.
Work Description: Mill and overlay pavement sur­face, reconstruct sidewalk (curb ramps and alley/ driveway crossings), construct multi-modal path from 16th Ave to RR underpass at 11th Ave.
Construction Timeframe: Between June & October
Cost: $1 million
Impact: Road Closure – 8th Street

Banks Blvd & Edison Blvd Reconstruction (SAP 038-632-003)

Location: City of Silver Bay

  • Banks Blvd (Horn Blvd to Davis Drive)
  • Edison Blvd (Penn Blvd to Horn Blvd)

Work Description: Street & Utility  Reconstruction (Water utility, sewers, curbs, side­walks, pavement).
Construction Timeframe: End of May thru October
Cost: $4-$5 million
Traffic Impacts: Road Closures:

  • Banks Blvd and Edison Blvd
  • Davis Drive at City Hall (short duration)

Highway 2 Reconditioning (SAP 038-602-036)

Location: Highway 2 (CSAH 2) Murphy Creek to Greenwood Lake Public Access
Work Description: Replace culvert pipes, reclaim ex­isting pavement and construct new pavement surface.
Construction Timeframe: June thru September
Cost: $3.4 million
Traffic Impacts: Lane closures, travel delays & 6-week Hwy 2 closure with detour (along Forest High­way 11 (CSAH 15), Lax Lake Road (CSAH 31) and MN Hwy 1).